Paving of the
parking lot at the Rue and Gwen Gibson Farm Market at Fresno
State is complete, and the parking area may be reopened during
the week of March 17.
Paving and other work
in the lot and surrounding areas are part of the Chestnut Avenue
widening project. Existing asphalt areas were torn out to create a new
and improved parking lot, including better driveway approaches, product
loading/unloading areas and designated parking stalls for persons with
disabilities.
During the week of
March 17, weather permitting, the final paving of Chestnut Avenue from
Barstow to Bullard will be undertaken. Because of the work, Barstow
Avenue will be closed from Woodrow to Willow Avenue during the week to
allow for the contractor to complete paving on each side of roundabout
at Barstow/Chestnut avenues. Preparation for paving of Shaw to Barstow
also will be done that week. Access to the Farm Market will be from Shaw
via Woodrow and Chestnut avenues. Message boards will direct drivers.
Barstow will reopen
during the week of March 24 and final paving will begin between Shaw and
Barstow avenues.
The paving has to “set”
prior to striping work. It is anticipated all of the work will be
completed by April 11 and approvals will be sought from the city of
Fresno to reopen the street.
Work remaining on the
project includes new traffic signal equipment at Shaw/Chestnut and
Bullard/Chestnut and widening of westbound lane from Highway 168 to
Woodrow Avenue in front of the Save Mart Center. |